piratius
Well-known member
Hey guys!
Two really quick questions. I'm approaching the point where I need to have the inspector come out and look at my wiring, boxes, and connections at the breaker panel. I have 12/2 run through the walls for 20A service, and 14/2 up in the ceiling for lighting, and boxes along the walls and ceiling (simple version). All that's left to do is tie everything in at the panel (simple) and join the safety grounds in all the boxes.
First up - The general contractor who built the structure said that I need to pull all the safety grounds together in the box and use a ground crimp to hold them all, and that they won't approve the use of wire nuts for the safety grounds anymore. Is that correct? It's no big deal for me to go buy a baggie of the little crimps, I just already have a ton of the correct size wire nuts because I thought I'd be able to use them for the project.
The second question - I know back in the "old times" they installed 240V circuits with 12/2 with ground - Black was Leg 1, White was Leg 2 (with red tape/flag on it), and the safety ground is the third prong.
Part 1) If I'm just running compressors/welders that just use 3 prong 240V, can I put in 3 wire outlets, or does all new work require the 12/3 with ground for a 4 wire outlet? (at which point, I would have to get an adapter, no biggie).
Part 2) If I do need to do 4 wire (12/3 w/ ground) 240V, can I run two strands of 12/2 into the box? Strand 1 would have leg 1 (black) and neutral, Strand 2 would have leg 2 (black) and neutral. Both Neutrals would be tied together at the outlet, and both safety grounds would be tied together as well. If that doesn't make sense, let me know and I'll explain better or try to draw it out and post it.
Thanks!
Two really quick questions. I'm approaching the point where I need to have the inspector come out and look at my wiring, boxes, and connections at the breaker panel. I have 12/2 run through the walls for 20A service, and 14/2 up in the ceiling for lighting, and boxes along the walls and ceiling (simple version). All that's left to do is tie everything in at the panel (simple) and join the safety grounds in all the boxes.
First up - The general contractor who built the structure said that I need to pull all the safety grounds together in the box and use a ground crimp to hold them all, and that they won't approve the use of wire nuts for the safety grounds anymore. Is that correct? It's no big deal for me to go buy a baggie of the little crimps, I just already have a ton of the correct size wire nuts because I thought I'd be able to use them for the project.
The second question - I know back in the "old times" they installed 240V circuits with 12/2 with ground - Black was Leg 1, White was Leg 2 (with red tape/flag on it), and the safety ground is the third prong.
Part 1) If I'm just running compressors/welders that just use 3 prong 240V, can I put in 3 wire outlets, or does all new work require the 12/3 with ground for a 4 wire outlet? (at which point, I would have to get an adapter, no biggie).
Part 2) If I do need to do 4 wire (12/3 w/ ground) 240V, can I run two strands of 12/2 into the box? Strand 1 would have leg 1 (black) and neutral, Strand 2 would have leg 2 (black) and neutral. Both Neutrals would be tied together at the outlet, and both safety grounds would be tied together as well. If that doesn't make sense, let me know and I'll explain better or try to draw it out and post it.
Thanks!
