rmack898
Well-known member
New house, new shop on 10 acres and utilities will be underground.
I met with the power company engineer to discuss my needs and where we are going to bring in power. I will have a 200amp service for the house and 200amp to the shop. We decided that I will put in a 400 amp, meter/2circuit panel that will be located between the house and the shop and each building will have its own 200 amp breaker. The run from the pole to the meter base is 215' and I have to put in the pipe. They want 3" pipe, 36" deep with 36" radius ells. All of this pipe run will be through forrest, is there any need for sch.80 pipe or will sch.40 be adequate?
Next question: The run from the meter base to the house is 115' and to the shop is 95'. I have no reference books here in my camper but my gut feeling is telling me that I'm going to need 1Ga copper (I'm not using aluminum) or can I get away with 2 Ga? Can I fit that in 2" pipe or do I need to run 3"?
I will be adding a data pipe while I have an open trench. My thought is 1" pipe from the pole to a j-box at the meter for a co-ax run, and then 1" from the j-box to the house for co-ax and cat5, and 1" from the j-box to the shop for cat5. Am I missing anything? I only want to dig once.
I met with the power company engineer to discuss my needs and where we are going to bring in power. I will have a 200amp service for the house and 200amp to the shop. We decided that I will put in a 400 amp, meter/2circuit panel that will be located between the house and the shop and each building will have its own 200 amp breaker. The run from the pole to the meter base is 215' and I have to put in the pipe. They want 3" pipe, 36" deep with 36" radius ells. All of this pipe run will be through forrest, is there any need for sch.80 pipe or will sch.40 be adequate?
Next question: The run from the meter base to the house is 115' and to the shop is 95'. I have no reference books here in my camper but my gut feeling is telling me that I'm going to need 1Ga copper (I'm not using aluminum) or can I get away with 2 Ga? Can I fit that in 2" pipe or do I need to run 3"?
I will be adding a data pipe while I have an open trench. My thought is 1" pipe from the pole to a j-box at the meter for a co-ax run, and then 1" from the j-box to the house for co-ax and cat5, and 1" from the j-box to the shop for cat5. Am I missing anything? I only want to dig once.