I have a brand new 24x34 3 car garage and I'm leaning heavily toward a checkerboard vct floor. I know there are many posts on this site regarding vct installation but I have a couple of specific questions.
1. What is the "working time" for the glue?
2. I know I won't be able to lay the whole floor at once so can I trowel glue over glue on day 2 ( i.e. area glued but not tiled on day 1 in case my knees can 't cover my ambitions)?
Thanks
Bud