Recent posts about setting slab forms reminded me of a project back in 2005 to build my 12x16 yard shed in the back yard. I came back from a work trip to find a gravel pad in the back yard for the shed. Not where I wanted it, but my ex-wife decided that was the location for it. Argh. We also "discussed" my plans for the shed. I said I had it covered as I had previously built two garages. We, ah, "discussed" it further, and she was convinced I needed to buy a set of shed plans for the eventual build. Never mind, bought the damn plans which I barely referenced as I built my own design anyway.

Ok, to the point. I planned to build the floor/deck all from treated lumber and 3/4" marine treated plywood, on concrete footing blocks, on the gravel pad. So I needed to get the blocks all leveled to each other for the deck framing. I used the old technique of a 5-gal pail of water near the center of the pad, water filled hose with a clear hose section at the end. Coil the hose into the bucket to fill it, add water to the bucket the expected level above grade. Once the hose is full of water, one end stays in the bottom of the bucket, the clear tube end is capped. Then I could take the clear hose end to the corners of the pad and confirm footing level by matching a stake height to the level of the water in the hose held vertically (water seeks level), matching the level of the water in the bucket.

As I was finishing up, my ex came out to question what I was doing, she watched me moving around the gravel pad leveling the blocks with the water bucket level, thought I was dicking around wasting time. We, again, ahh, "discussed" my process and SHE insisted I invite a guy over that she knew worked for the county, with his professional laser transit. Ok, ok, call him over so I can move on! I felt bad to hassle the guy. He comes over, as he walks across the yard, sees my device and says "Hey, a water bucket level, those are accurate!" I stifled my smirk. He proceeded to set up the transit on her request, and confirmed I was within a 1/8" of level on the 20' diagonal.

So anyway, if you need to set up concrete forms level or at a slight pitch even on a large area, a water bucket/hose level system works great and is very accurate. Sub-story, I should grown a pair before getting into the various "discussions" with my ex. All good though, she is long gone and I'm remarried to the right one all along.
 
To avoid these ads, REGISTER NOW!

Shiftless

Well-known member
Joined
Mar 9, 2014
Messages
14,969
Location
East Bay SFO
I remodeled an old house in Spain, 1966 to 1969 using 20 Meters of clear tubing and water as a level.

I bet that guys double check their laser levels using a long distance pair of points determined by a water level.

BTW, what’s the correction factor when checking a laser against a water level taking into consideration the curvature of the earth? :)
 
To avoid these ads, REGISTER NOW!
OP
A

andyvh1959

Well-known member
Joined
Feb 15, 2020
Messages
2,631
Location
Green Bay WI
20 meters, hmm, over 66' of tubing, makes it even more accurate.

When I built my 1st garage way back in 1980, a modest 16x20, my 1st wife's dad and grandpa came over to help me set up the concrete forms. I let them lead as it was my 1st build. But an argument ensued between dad/grandpa over which end of an 8' level should get the 1/4" shim to determine the pitch of the slab to drain out to the OH door. After a couple of "Ya dumb SOB! It goes under this end!" and "No, this end!!" I let it play out, being the new guy on the job. Well, the winner was wrong, as a hard rain from the east would have water sneak under the OH door and collect at the back.

I think "dad" was the winner, and we still chuckle about it to this day. Grandpa was right.
 
Last edited:
To avoid these ads, REGISTER NOW!
Top Bottom