mrobins297aaa
Well-known member
I had a contractor put up a pole barn for me last fall 36' x 64'.
With winter and all the mud I really haven't had that much of a chance to check it out and layout all my stuff until now.
well come to find out the building measures 34' x 64'
when this was being erected I really watch them and checked out I thought everything.
he submitted plans to the city showing the trusses 36' with a 12" over hang on the eves which would make 38' overall.
In hind sight i'm sure I know what happen, who ever ordered the trusses forgot to add the 12" over hangs on each side so the trusses came exactly 36'
I'm sure the first thing the carpenter did when he layout the building was measure those trusses and build the building based on there length.
what gets me is this contractor I hired did nothing, he took a deposit (which later it was obvious that was his profit) and after that I only seen him once. he had it set up that when the lumber came I payed them direct and when the building was done I paid the carpenters.
what would you guys do?
With winter and all the mud I really haven't had that much of a chance to check it out and layout all my stuff until now.
well come to find out the building measures 34' x 64'
when this was being erected I really watch them and checked out I thought everything.
he submitted plans to the city showing the trusses 36' with a 12" over hang on the eves which would make 38' overall.
In hind sight i'm sure I know what happen, who ever ordered the trusses forgot to add the 12" over hangs on each side so the trusses came exactly 36'
I'm sure the first thing the carpenter did when he layout the building was measure those trusses and build the building based on there length.
what gets me is this contractor I hired did nothing, he took a deposit (which later it was obvious that was his profit) and after that I only seen him once. he had it set up that when the lumber came I payed them direct and when the building was done I paid the carpenters.
what would you guys do?