When to pour concrete floor for pole barn

dneiding

Well-known member
Joined
Jan 16, 2017
Messages
161
Location
North Central Ohio
I am getting ready to build a 24x40 pole barn and wondering if there is any issue with pouring the floor after the posts are set and before any walls are built?

Every video I see or every time I have seen someone build a pole barn the do the floor after the building is complete. I was thinking it might be easier to do it earlier in the process.

My idea is to set the posts, plumb them, put the grade boards on and then pour the floor. My thinking is without the walls and headers over the overhead doors it will be so much easier to get the concrete truck close to the pour. Also, seems like floating would be a whole lot easier without the walls and roof on.

I will be doing the concrete work myself with help from friends.

Any thoughts?
 
Last edited:
To avoid these ads, REGISTER NOW!

TractorJeff

Well-known member
Joined
Dec 8, 2013
Messages
3,309
Location
Elkhorn, WI
I see no reason if its well compacted. Make sure that some of your friends actually know how to pour concrete! Feed them well after its done!
 
To avoid these ads, REGISTER NOW!

larry_g

Well-known member
Joined
Apr 28, 2007
Messages
16,932
Location
oregon
In my build we had the poles, girts, trusses and roofing on, then poured before the side metal went on. We also used a pump to move the concrete into the building. $300 forthe pump and I considered it money well spent.

In your case I would think it would be wise to get as many girts and headers on as you can to hold the poles in place. If you have to leave out those girts that get in the way then do so.

lg
no neat sig line
 