Wiring after insulation or before?

neblinc

Well-known member
Joined
Apr 18, 2006
Messages
424
Location
Lincoln, NE
Ok Guy's I am getting close to finishing up the framing inside my shop.
Do I run my electrical now and keep it behind the insulation or put it in after I hang the insulation?

I have space behind my framed walls between the steel siding & the 2 x 4's so I was thinking I should do the electrical first?

Randy
 
To avoid these ads, REGISTER NOW!

rworkman98

Member
Joined
Jul 31, 2006
Messages
24
neblinc said:
Ok Guy's I am getting close to finishing up the framing inside my shop.
Do I run my electrical now and keep it behind the insulation or put it in after I hang the insulation?

I have space behind my framed walls between the steel siding & the 2 x 4's so I was thinking I should do the electrical first?

Randy


I would definately do electrical before insulation. Insulation is nasty stuff, and I'd rather be in as little contact with it as possible. When I built my garage, I did electrical first, even though I ran my EMT near the front of my 2x4s, and had to shove the insulation behind them.. It was still much easier to run the electrical first.
 

DOM!

Member
Joined
Mar 1, 2006
Messages
17
Location
Connecticut
neblinc said:
Ok Guy's I am getting close to finishing up the framing inside my shop.
Do I run my electrical now and keep it behind the insulation or put it in after I hang the insulation?

I have space behind my framed walls between the steel siding & the 2 x 4's so I was thinking I should do the electrical first?

Randy

Most definately before the insulation..
 
To avoid these ads, REGISTER NOW!

boiler7904

Well-known member
Joined
Apr 4, 2006
Messages
3,414
Location
NW IN
Before. Inspectors will want to see the wall cavities before insulation blocks view of any electrical j-boxes, conduit runs, etc. and framing details like fire / draft stopping, hurricane straps and the like.
 
Last edited:

The Money Pit

Well-known member
Joined
Dec 6, 2005
Messages
137
Location
Virginia
1. Footing
2. Pad/foundation
3. Framing
4. Electrical/Plumbing/HVAC
5. Insulation
6. Drywall
7. Everything else

#'s 1 & 2 can be swaped.
 