A&P mechanic
Well-known member
Hi,
I need to make concrete forms 20 inches high with a 4 inch curb on the inside per the PDF drawing. I included an example picture of a similar monolithic slab pour that includes the curb.
What size wood should I use for the 20 inch concrete forms?
What size wood or alternative should be used as stakes?
I am considering stacking (2) 2 x 12s which would be 22 ½ inches then I would bury the extra 2 ½ inches, so I do not have to rip the extra 2 ½ inch off on my table saw. I see 36 inch rebar pins at Lowes and am considering those instead of wooden stakes. I see 36 inch 1 x 2 wooden stakes at Lowes but they seem kind of thin. 2 x 12s are expensive. I am willing to get 2x12s but am also looking for an opinion on ¾” plywood as an alternative. I am building the forms, putting the rebar, vapor barrier down etc. I am paying to have a pump truck do the pour and am paying to have the slab finished.
Another question. I plan to have 6 inches of gravel (lime stone) + 14 inches of concrete underground then 6 inches of concrete above ground (4 inch curb + 2 inch of slab sticking up). Did I interpret the drawing correctly?
I finished digging and am having 8 yards of lime stone delivered next weekend as a base below the concrete.
Thank you in advance!
I need to make concrete forms 20 inches high with a 4 inch curb on the inside per the PDF drawing. I included an example picture of a similar monolithic slab pour that includes the curb.
What size wood should I use for the 20 inch concrete forms?
What size wood or alternative should be used as stakes?
I am considering stacking (2) 2 x 12s which would be 22 ½ inches then I would bury the extra 2 ½ inches, so I do not have to rip the extra 2 ½ inch off on my table saw. I see 36 inch rebar pins at Lowes and am considering those instead of wooden stakes. I see 36 inch 1 x 2 wooden stakes at Lowes but they seem kind of thin. 2 x 12s are expensive. I am willing to get 2x12s but am also looking for an opinion on ¾” plywood as an alternative. I am building the forms, putting the rebar, vapor barrier down etc. I am paying to have a pump truck do the pour and am paying to have the slab finished.
Another question. I plan to have 6 inches of gravel (lime stone) + 14 inches of concrete underground then 6 inches of concrete above ground (4 inch curb + 2 inch of slab sticking up). Did I interpret the drawing correctly?
I finished digging and am having 8 yards of lime stone delivered next weekend as a base below the concrete.
Thank you in advance!






