motormitch
Well-known member
My builder had the foundation for my slab formed in, sandbagged perimeter and the rough plumbing installed with plans to pour the weekend. The foundation is on a slope and is 7 feet elevated on the back wall and one side wall. We just had a VERY heavy rain and when I checked the job site the sand bags had partially collapsed toward the form walls. In some places is actually sifts all the way over and actually touched. There are large sections where the sandbagged edge will clearly have to be completely redone. First the builder believed that we would wait a few days to dry out and then rebag. This would impact the pour about 1 week. Then he meet with the foundation engineer and here is what he just emailed me.
------------------------------------------------------------------------
After consulting with Roberto at CRI , two other concrete subs and Baldi (this afternoon) we need everything to dry out before continuing and that once the bag form walls are repaired half way we will pour concrete up to that point called a (weather stop pour) which will be inspected by Matt from CRI so we are pushing for a partial pour this Thursday coming and the final top out pour Monday the 15Th leaving 2 weeks to cure we also will the back parking poured and the front formed and graded before bldg arrives
-------------------------------------------------------------------------
I can't seem to find anything about a weather stop pour except for very cold weather or pouring in a heavy rain. Does this make sense or should I insist on a different plan. This is a big building (to me) 70'x55' It is also a post tension foundation.
Guide me oh great ones who have gone before me...
------------------------------------------------------------------------
After consulting with Roberto at CRI , two other concrete subs and Baldi (this afternoon) we need everything to dry out before continuing and that once the bag form walls are repaired half way we will pour concrete up to that point called a (weather stop pour) which will be inspected by Matt from CRI so we are pushing for a partial pour this Thursday coming and the final top out pour Monday the 15Th leaving 2 weeks to cure we also will the back parking poured and the front formed and graded before bldg arrives
-------------------------------------------------------------------------
I can't seem to find anything about a weather stop pour except for very cold weather or pouring in a heavy rain. Does this make sense or should I insist on a different plan. This is a big building (to me) 70'x55' It is also a post tension foundation.
Guide me oh great ones who have gone before me...
