Not that it matters for you but for anyone else doing this, look at the last picture with the 90* in the trench. Could have done a 45* or even a gentle curve and made wire pulling a lot easier. Doing it the way shown eats up your 360* of bend quickly.
I know, and i hate it, however did not want to get the ditchwitch near the brick, that is a slight slope there, and the soil was soft.
I have not buried the conduit yet, if it proves difficult, then i can attempt to redo it, if cables pass, then its a go....
For a first time handling a 36 trencher, i say im pleased. but i know its not perfect.... lol
And by they way.... if anyone wants to know, i was able to go under 7 feet of driveway by using a planting auger....
used a drill and several drill bit extensions. and perfect for a 2 inch pipe.
cheap, but labor intensive......