fotoflojoe
Well-known member
Guys,
Fairly soon, I'll be installing a sub panel. After much research and reading, I've gotten everything figured out - almost.
- Main service in house is 200 amps
- Sub panel will be 100 amp
- The garage is 30 feet from the house
- Pulling 3 #3 THWN and 1 #CU Ground through 1.5" schedule 40 conduit
(Conduit is already in place)
- Burying 2 8 foot ground rods within six feet of sub panel
For me, the devil is in the details:
Where cable enters the house, does it need to pass through a junction box, or can the cable come through the LB fitting/joist and then be directly fastened along a joist?
Does the cable need to enter the garage above the sub panel? Or, can it come in below and be routed up into the panel?
Haven't been able to find any information on these points. They might seem like silly questions to some, but they're the kind that drive me nuts.
Fairly soon, I'll be installing a sub panel. After much research and reading, I've gotten everything figured out - almost.
- Main service in house is 200 amps
- Sub panel will be 100 amp
- The garage is 30 feet from the house
- Pulling 3 #3 THWN and 1 #CU Ground through 1.5" schedule 40 conduit
(Conduit is already in place)
- Burying 2 8 foot ground rods within six feet of sub panel
For me, the devil is in the details:
Where cable enters the house, does it need to pass through a junction box, or can the cable come through the LB fitting/joist and then be directly fastened along a joist?
Does the cable need to enter the garage above the sub panel? Or, can it come in below and be routed up into the panel?
Haven't been able to find any information on these points. They might seem like silly questions to some, but they're the kind that drive me nuts.