Currently framing my garage with living space on my own. I’m having trusses delivered on Monday. I want to do a 12-18” overhang on the gable end. I’m trying to figure out how to frame it.
I would love to have the zip r6 fly all the way to the roof line and lay the ladder frame on top of the zip but I’m not sure how much weight the zip will hold with the ladder frame on it until the roof sheathing is on.
My other option is to put the ladder frame directly on the gable end and then put the R6 up to it on the bottom.
What do you guys think would be best. Trying to figure out all the details of sheathing around decks and the roof is quite some work compared to regular OSB sheathing with no foam on it.
Here’s some pictures of my progress so far.
Keeping the front gable end wall down until the crane starts dropping off a few trusses on Wednesday. On the right side I have my deck ledger on the rim joist with the zip sheathing up to it. It will get covered with zip flashing tape soon.
30’x40’
12’3” first floor open floor plan
16” TJIS with LVL flanges.
9’2 second floor walls
Energy heel trusses 8/12 pitch
I would love to have the zip r6 fly all the way to the roof line and lay the ladder frame on top of the zip but I’m not sure how much weight the zip will hold with the ladder frame on it until the roof sheathing is on.
My other option is to put the ladder frame directly on the gable end and then put the R6 up to it on the bottom.
What do you guys think would be best. Trying to figure out all the details of sheathing around decks and the roof is quite some work compared to regular OSB sheathing with no foam on it.
Here’s some pictures of my progress so far.
Keeping the front gable end wall down until the crane starts dropping off a few trusses on Wednesday. On the right side I have my deck ledger on the rim joist with the zip sheathing up to it. It will get covered with zip flashing tape soon.
30’x40’
12’3” first floor open floor plan
16” TJIS with LVL flanges.
9’2 second floor walls
Energy heel trusses 8/12 pitch