Hi All!
I hired a company to do my pour. I did an 8" slab, in floor heat, with an 18" thickened edge footing.
32 MPa, 5-8%. Pour took about 3 hours, and the crew finished the floor (smooth) for about 3 additional hours. They were good, hand screeded, hand trowel, then finished with a couple different pads on the power trowel.
it was a pretty cool day. 68F as the high. Pad was nearly completely in the shade when the guys finished. We wet it lightly and they told me to wet it a few more times that night, and again in the morning.
Today when I got home from work (~26 hours after they finished), I saw some cracks, which I was fine with, but as I walked on it, I could hear crunching. Tapping on the floor in most spots feels hollow, and some of it was moving considerably. I think about 1/8" on top has separated over most of the pad.
See pics. What can be done? What should I expect them to do? Right now, theyre claiming maybe it was bad concrete from the supplier.
I hired a company to do my pour. I did an 8" slab, in floor heat, with an 18" thickened edge footing.
32 MPa, 5-8%. Pour took about 3 hours, and the crew finished the floor (smooth) for about 3 additional hours. They were good, hand screeded, hand trowel, then finished with a couple different pads on the power trowel.
it was a pretty cool day. 68F as the high. Pad was nearly completely in the shade when the guys finished. We wet it lightly and they told me to wet it a few more times that night, and again in the morning.
Today when I got home from work (~26 hours after they finished), I saw some cracks, which I was fine with, but as I walked on it, I could hear crunching. Tapping on the floor in most spots feels hollow, and some of it was moving considerably. I think about 1/8" on top has separated over most of the pad.
See pics. What can be done? What should I expect them to do? Right now, theyre claiming maybe it was bad concrete from the supplier.