I'm close - maybe about a week or two away - from finalizing a gas line to my barn/workshop. The line was directional bored (proper tracer wire, proper gas poly), so all that's left is digging a trench between where the line came out and the building. This isn't as easy as it should be as a water line was pulled in the same pull, and I have to dig both down to depth (here it's about 54"!).
I have about 8-16" of concrete above grade where I'd like to bring the line in. I'm running a 1" line, and would continue that 1" pipe through the foundation wall.
From what I've read, it must be sleeved and the sleeve has to be 2 times the pipe size - so 1-1/2" (2 trade pipe sizes larger?).
Wondering if anyone has done this before, gotten it inspected and approved. I'm really leery of going through my siding, insulation, etc... so would like to core through the concrete. Don't ask why I didn't put a sleeve in... at the time I wasn't really thinking I guess.
You can see the corner when the foundation was first put in:
And with siding:
I don't have a closeup, but the siding sits about 6" away from the foundation. I'm going to be bringing the grade up on the other side by about 10", which will leave 8-16" of foundation exposed.
I have about 8-16" of concrete above grade where I'd like to bring the line in. I'm running a 1" line, and would continue that 1" pipe through the foundation wall.
From what I've read, it must be sleeved and the sleeve has to be 2 times the pipe size - so 1-1/2" (2 trade pipe sizes larger?).
Wondering if anyone has done this before, gotten it inspected and approved. I'm really leery of going through my siding, insulation, etc... so would like to core through the concrete. Don't ask why I didn't put a sleeve in... at the time I wasn't really thinking I guess.
You can see the corner when the foundation was first put in:
And with siding:
I don't have a closeup, but the siding sits about 6" away from the foundation. I'm going to be bringing the grade up on the other side by about 10", which will leave 8-16" of foundation exposed.