Made the first large mistake in my build of the garage. Could be a costly one to correct.
New slab poured yesterday. It is 4.5in or 4000psi concrete with an extra area of 3.5ftx3.5ft that is 8in deep where the 2 post lift is supposed to go. It seems I forgot to tell the contractor those areas needed rebar. I unfortuantely only have wiremess in the entire slab now.
The plan is to install a BendPak 10APX lift.
https://www.bendpak.com/10apx/ It does clearly state #6 rebar is needed. My mistake on this one. I should have sent the lift specs to the contractor so that nothing was missed.
A call to BendPak actually yielded unsuspecting answer though. The gentleman I spoke with said it should be fine although they still suggest rebar. So my question to those here, am I playing with fire by not cutting out a section of the brand new slab and having two pads poured to the BendPak existing concrete install specs with rebar?