12x40x48 post building moving along slowly.
Getting things together for a flooring quote. Slab will be non structural, and poured after the building is erected.
Plan on installing my bendpak 10k 2 post lift towards the center of the building.
Bendpak recommends a minimum thickness of 4.25 in. (108 mm) 3,000 PSI / 28 Day Aging and #6 Rebar (3/4"), and spacing of 12 in.
I was planning on using 6" of concrete, a contractor also suggested adding wire mesh as well.
Any comments?