Hello Everyone!! I am installing a Triumph C7000 2 Post lift in my garage and I have an issue with getting it level. I poured 2 3x4 concrete footings which are level front to back and about 1/16 off side to side due to slope out in garage floor. I drilled all of the anchor bolts and set both posts with no issues. I had to put 2 1/16th inch shim on the one side of both posts to level for slope in garage floor so it is perfectly level side to side. When I measure the distance between the 2 post top and bottom there is a 1 1/2 inch difference (wider at the top) How ever the bases are perfectly level and so is the concrete pads. I have to shim the back of both posts about a 1/2 inch to get it plumb. Is it possible the bases where not welded square to the posts?? Am I missing something here?? How much can you shim the posts before you have to pour a filler under the pad??