Alright guys I am building a 2 story 3100 sq foot house and I the builders HVAC company screwed up and I want to see what some other guys thoughts are.
The specs per our contract call for 2 systems 92% for both heat and AC. However when I got there the other day after the duct work was ran I came across a single 80% system. I know swapping out the 80 for the 92% is easy.
However my question comes from what is the CORRECT way to run the return air for a second system that feeds only the upstairs?
Currently it is running from every room upstairs through the floor into the wall and ties into the main floor return. (like every other single system).
I think the upstairs returns should be ran into a single return duct in the attic and then drop down into the basement to feed the system.
The specs per our contract call for 2 systems 92% for both heat and AC. However when I got there the other day after the duct work was ran I came across a single 80% system. I know swapping out the 80 for the 92% is easy.
However my question comes from what is the CORRECT way to run the return air for a second system that feeds only the upstairs?
Currently it is running from every room upstairs through the floor into the wall and ties into the main floor return. (like every other single system).
I think the upstairs returns should be ran into a single return duct in the attic and then drop down into the basement to feed the system.