Good day been here for some time but this is my first post and I need some advice.
After many years of delays I have started building my shop. It is a slab on grade 30x40x12 the biggest my township will allow. Currently site prep is done concrete forms are in place and the concrete trucks are booked for next week.
This will be my 4th slab that I have poured so I am not worried about the work involved. However since prices of everything have gone through the roof I do not want to order too much concrete.
Right now concrete is over $300 a yard in my area.
Slab is a 18"x12" thickened edge tapered up at 45 to 6" floor. I calculated the amount need just under 30 yards.
Now I have always order some extra to insure I has the right amount to finish the job, but I have never had the amount of rebar, wire mesh and pex in the slab that I have in this one.
So my question is should I take these items into account when ordering the concrete and not order extra or even order less then the 30 yards?
If ordering less then the 30 yards what is the best way to calculate the volume of the mesh.
600 feet of 5/8" rebar
1160 sq feet of 6x6x6 mesh
1250 feet of 1/2 pex
Thank you
After many years of delays I have started building my shop. It is a slab on grade 30x40x12 the biggest my township will allow. Currently site prep is done concrete forms are in place and the concrete trucks are booked for next week.
This will be my 4th slab that I have poured so I am not worried about the work involved. However since prices of everything have gone through the roof I do not want to order too much concrete.
Right now concrete is over $300 a yard in my area.
Slab is a 18"x12" thickened edge tapered up at 45 to 6" floor. I calculated the amount need just under 30 yards.
Now I have always order some extra to insure I has the right amount to finish the job, but I have never had the amount of rebar, wire mesh and pex in the slab that I have in this one.
So my question is should I take these items into account when ordering the concrete and not order extra or even order less then the 30 yards?
If ordering less then the 30 yards what is the best way to calculate the volume of the mesh.
600 feet of 5/8" rebar
1160 sq feet of 6x6x6 mesh
1250 feet of 1/2 pex
Thank you

