Hi Guys,
I took a lot of useful information from this site over the last couple years and thought I would show what I've done. Appreciate all the help!
I hand sketched the drawings and submitted for permits early June 2020 and got approved July 7th. 32x44x12' with 7/12 attic trusses and a 12' lean to off one gable end. 2 - 10x10, 1 - 7x8 garage doors, 3 man doors and 3 windows (+2 windows in the attic).
The first day of actual work was June 20th, 2020. Removed trees and brush first. Saved 9 red oak and 2 cherry logs and had a guy bring his portable mill to my site after the rough digging was done. Stacked the lumber and let everything sit over the winter.


Easter weekend of 2021 I rented a mini and dug the footer and ditch back to the house.


Formed and poured the footer then started laying block by the end of April. Finished laying block and parging mid May. Grouted every cell with rebar as appropriate and set the anchor bolts.


Backfilled, insulated, ran pex and poured the pad in June.



At this point I had to make the call if I was going to go for it or not. Got the OK to frame with rough cut (to avoid the terrible lumber costs), so I went for it. Started framing early July and finished the sheathing early September, ready for trusses. I watched sheet prices like a hawk and ordered when pricing was reasonable.

To be continued.
I took a lot of useful information from this site over the last couple years and thought I would show what I've done. Appreciate all the help!
I hand sketched the drawings and submitted for permits early June 2020 and got approved July 7th. 32x44x12' with 7/12 attic trusses and a 12' lean to off one gable end. 2 - 10x10, 1 - 7x8 garage doors, 3 man doors and 3 windows (+2 windows in the attic).
The first day of actual work was June 20th, 2020. Removed trees and brush first. Saved 9 red oak and 2 cherry logs and had a guy bring his portable mill to my site after the rough digging was done. Stacked the lumber and let everything sit over the winter.


Easter weekend of 2021 I rented a mini and dug the footer and ditch back to the house.


Formed and poured the footer then started laying block by the end of April. Finished laying block and parging mid May. Grouted every cell with rebar as appropriate and set the anchor bolts.


Backfilled, insulated, ran pex and poured the pad in June.



At this point I had to make the call if I was going to go for it or not. Got the OK to frame with rough cut (to avoid the terrible lumber costs), so I went for it. Started framing early July and finished the sheathing early September, ready for trusses. I watched sheet prices like a hawk and ordered when pricing was reasonable.

To be continued.

























