Well i thought i would throw up some pics of the build, havn't had a lot of time as i've been busy at work. I had to get engineered drawings for the build because of the size and the ground work began in the spring of last year.
Tearing out the old pad after deciding it was going to less of a hassle for the new pad
Gutter drain installed
foam laid for radiant floor
tubing installed 12 runs
I did take a lot of pictures of all tubing because i am planning on installing a 2 post hoist at the back wall
Pouring of the pad was 5 1/2"
and done
Some walls going up
and this is where i left it before it took off back to work after christmas
I hired a contractor to finish it off and they have just been cruising along its kinda funny at the end of the day they get so much more accomplished then i ever would have haha
Here the front roof has been installed and the back is about a quarter complete
and thats all for now garage doors are coming in a few weeks and the ditch for the 200amp service and other goodies is going to be dug next week so the electrician can run some power to the inside
Tearing out the old pad after deciding it was going to less of a hassle for the new pad
Gutter drain installed
foam laid for radiant floor
tubing installed 12 runs
I did take a lot of pictures of all tubing because i am planning on installing a 2 post hoist at the back wall
Pouring of the pad was 5 1/2"
and done
Some walls going up
and this is where i left it before it took off back to work after christmas
I hired a contractor to finish it off and they have just been cruising along its kinda funny at the end of the day they get so much more accomplished then i ever would have haha
Here the front roof has been installed and the back is about a quarter complete