Had to add some wiring to my new garage, it was drywalled so went with EMT and very happy with the outcome, looks nice and lots of room to add more.
Ran 6/3 with 60amp breaker from House panel to sub panel:
1" EMT from Sub Panel to 12x12 junction box, 3/4" EMT down to Compressor plug
3/4" EMT to 4x4 Junction box, then to Welder Plug (NEMA 6-50P)
Once I get the highlift mod done to the single door I will be added a run of 3/4" EMT to front of hoist so I can plug it into the ceiling. I will also be adding some plugs on the hoist side wall (dropping 3/4" EMT down from junction box).
I used 50amp breaker with #6 wire for welder, 15amp breaker with #10 wire for compressor (240v) for future. Hoist will be 30amp #10 wire.
Ran 6/3 with 60amp breaker from House panel to sub panel:
1" EMT from Sub Panel to 12x12 junction box, 3/4" EMT down to Compressor plug
3/4" EMT to 4x4 Junction box, then to Welder Plug (NEMA 6-50P)
Once I get the highlift mod done to the single door I will be added a run of 3/4" EMT to front of hoist so I can plug it into the ceiling. I will also be adding some plugs on the hoist side wall (dropping 3/4" EMT down from junction box).