First time poster. Apologies if this is the wrong place to ask. I am building a barndominium all red iron. When we poured the slab we ripped a 2x4 and nailed it on the inside of the concrete forms to create a ledge for the sheet metal. We did use a rotary laser level for the height but I have noticed some minor imperfections.
Would anyone recommend using a piece of base trim all the way around or should we just set the sheet on the concrete?
First time poster. Apologies if this is the wrong place to ask. I am building a barndominium all red iron. When we poured the slab we ripped a 2x4 and nailed it on the inside of the concrete forms to create a ledge for the sheet metal. We did use a rotary laser level for the height but I have noticed some minor imperfections.