This was actually mostly built 2 years ago. The lean to at the end I did in the last month. Though you fellas might like to see the buildalong.
Did nearly all the work myself. Hand drew the blueprints. Pulled the permits. Everything but the concrete which I formed up myself and the garage doors.
Clearing and site prep. OK did not do this myself per say but hired a family friend at a steep discount.
16 tons of crusher run moved by hand.
Starting on posts. I used marine grade timbers for this. Termite proof and will last longer than I will live.
Did nearly all the work myself. Hand drew the blueprints. Pulled the permits. Everything but the concrete which I formed up myself and the garage doors.
Clearing and site prep. OK did not do this myself per say but hired a family friend at a steep discount.
16 tons of crusher run moved by hand.
Starting on posts. I used marine grade timbers for this. Termite proof and will last longer than I will live.