Had a new garage build 26X32, and the contrator wants to put contraction joints in the floor. He wants to make a cross in my floor, so cut from the middle of the 26 feet and one cut from the middle of the 32 feet. I have a drain in the center of the floor so the cutting would stop there. Also the cement is 4 inch thick. Now the floor was poured like 3 weeks a go, some people are telling me it's too late, that they should have done it way earlier, but the contractor is saying that it is ok to wait that long. Just want to make sure I will not be doing this contraction joints for nothing...?