Im in the process of setting up a blasting cabinet and powder coat oven in in area and would like my plan checked.
Run 1
6/2 or 6/3 Stove has 3 pronger on it now. If you insist I can add a 4 prong and go that way. But the jist is the 6 gauge with a 50 amp breaker.
I should be good there correct? Be nice to use the three prong cord...save me a couple bucks. Run will be about 10ft from my 200 amp panel. Have 15 open slots.
Run 2
3 outlets. 10/2 with a 20 amp breaker. Just a little run with 3 outlets chained together. Nothing more than a 15 amp power tool through this.
Run 3
Single pole switch to 2 celing outlets for 3 double tube florescent lights. 10/2 with a 20 amp or 12/2 with a 15 amp breaker? Just 3 lights on this one...thats all. Prefer not to hardwire as lights may change in future.
My box is a murray. Anyone know breaker type off top of head?
Thanks.
Run 1
6/2 or 6/3 Stove has 3 pronger on it now. If you insist I can add a 4 prong and go that way. But the jist is the 6 gauge with a 50 amp breaker.
I should be good there correct? Be nice to use the three prong cord...save me a couple bucks. Run will be about 10ft from my 200 amp panel. Have 15 open slots.
Run 2
3 outlets. 10/2 with a 20 amp breaker. Just a little run with 3 outlets chained together. Nothing more than a 15 amp power tool through this.
Run 3
Single pole switch to 2 celing outlets for 3 double tube florescent lights. 10/2 with a 20 amp or 12/2 with a 15 amp breaker? Just 3 lights on this one...thats all. Prefer not to hardwire as lights may change in future.
My box is a murray. Anyone know breaker type off top of head?
Thanks.