I have been reading this board for a while but have never made a post. Now that I have finally finished my shop (are shops ever really done?), I feel the need to show others what I have done. My shop is comprised of a 40x50 metal building with a 16' eave height. One side (1000 SF) is unfinished and used as garage space. The other side is two stories, providing 400 SF air condition office space (first floor), 600 SF air conditioned shop space (first floor), and 1000 SF of storage space (second floor).
With some help from my wife, I did all the work except for 1) the building pad, 2) the concrete foundation 3) the insulated metal building shell, 4) the load center, 5) the drywall finishes and 6) the insulation.
So, off the the races. The building pad is 12 inches high and was put in at unknown cost as part of the house which I was building at the same time on the same site ("free" per the contractor but I know I really paid for it somewhere). The building was elevated because the site is very flat and experienced flooding during heavy rainfall. You will see some photos showing why this was a VERY good idea.
View media item 85341
I am a structural engineer and I designed the foundation. Given that it is a light duty building, I used a 5 inch slab with #4 bars at 14 inches on-center. The metal building was supplied by Mueller and the anchor rods were designed using their supplied base reactions.
View media item 85342
View media item 85343
View media item 85344
With some help from my wife, I did all the work except for 1) the building pad, 2) the concrete foundation 3) the insulated metal building shell, 4) the load center, 5) the drywall finishes and 6) the insulation.
So, off the the races. The building pad is 12 inches high and was put in at unknown cost as part of the house which I was building at the same time on the same site ("free" per the contractor but I know I really paid for it somewhere). The building was elevated because the site is very flat and experienced flooding during heavy rainfall. You will see some photos showing why this was a VERY good idea.
View media item 85341
I am a structural engineer and I designed the foundation. Given that it is a light duty building, I used a 5 inch slab with #4 bars at 14 inches on-center. The metal building was supplied by Mueller and the anchor rods were designed using their supplied base reactions.