Epoxy detail around a drain

climb.on

Well-known member
Joined
Apr 13, 2015
Messages
501
Location
Minnesota
In the attached garage we taped off the edge of the plastic channel drain. See first 2 pics. I feel like because the epoxy and clear coat is so thick, it left a decent size lip that seems like it will fail rather quickly. Especially since this is where all the crud will be flowing around. I filled all the control joints with a flexible polyurea joint filler, but I wonder if it's the right thing here next to the drain. Perhaps a hard epoxy filler would be better in this spot...

I'm about to do my shop next, but would like a better result. I'm thinking of extending the epoxy right to the inside edge of the channel and not taping it off like the attached garage. Channel drain is made of polypropylene I think.

What's best practice in this situation?
 

Attachments

  • IMG_6330.jpg
    IMG_6330.jpg
    127.2 KB · Views: 97
  • IMG_6331.jpg
    IMG_6331.jpg
    130.2 KB · Views: 86
  • IMG_6356.jpg
    IMG_6356.jpg
    143.4 KB · Views: 88
  • IMG_6357.jpg
    IMG_6357.jpg
    145.6 KB · Views: 88
To avoid these ads, REGISTER NOW!
OP
C

climb.on

Well-known member
Joined
Apr 13, 2015
Messages
501
Location
Minnesota
Anyone have thoughts about filling seams after putting down the epoxy? I don't really care to much about "hiding" the seams under the epoxy, I just want to eliminate the weak points where it might eventually fail.
 

Armorpoxy

Well-known member
Joined
Aug 18, 2013
Messages
3,735
Location
NJ
One of the things we recommend around drains when possible is to cut in a small 'slot' with an angle grinder and cut wheel. The 100% solids epoxy 'runs into' the slot and makes a definitive stop point that shouldn't chip or peel. This only works with 100% solids epoxies as they will cure at almost any thickness.
 
To avoid these ads, REGISTER NOW!

LegacyIndustrial

ALLIANCE MEMBER
Joined
Jun 7, 2010
Messages
7,994
Location
deerfield, IL
What does "key" mean? Round over the corner of the joint? Make it wider? Both?

Grinding down the edge so that the liquid coating will be "fat" right at the edge.




2bc9c37603adce677d874cfd3c4a1b58.jpg




Sent from my iPhone using Tapatalk
 
Last edited:
OP
C

climb.on

Well-known member
Joined
Apr 13, 2015
Messages
501
Location
Minnesota
Perfect thank you. I'll do that! Do you suggest epoxy first, then a joint filler filler over the top to fill the key?
 

LegacyIndustrial

ALLIANCE MEMBER
Joined
Jun 7, 2010
Messages
7,994
Location
deerfield, IL
The coating should be allowed to fill the key.
Once cured it should look level like the rest of the floor.

The only coating that can be used to fill the key is 100% solids epoxy. Anything else will bubble and make a mess.
 
OP
C

climb.on

Well-known member
Joined
Apr 13, 2015
Messages
501
Location
Minnesota

Don't call me that :scared:

.

If you put flexible joint filler on first then coated over it. You have cracks waiting to happen now.

Hope you didn't do that...

I did. I am expecting some cracks in the control joints...and probably else where too. But I'll have fewer of them than if I filled the joints after the fact. Now around the drain, I wish I would have filled the joint after. I'm going to do it that way in the other building. But all the other control joints are getting filled first.
 