KevinEF7
Active member
Hi guys, just looking into some suggestions on if this project would be worth my while or not, I just moved into this house that has a roughly 20 X 20 2 car garage with low ceilings. We noticed that this old triple 2 X 6 main beam (true 2x6 wood mind you, house/garage is very old) has some sag to it, and all of the joists running front to back have a good sag towards this center beam aswell
They are run on 24" center and right now the previous owner placed OSB ontop of the joists and then a ton of insulation up there to try and insulate the garage. The OSB and insulation will be coming out as its seen better days, aswell as all of the old electrical/garage door openers. But I am unsure of how to go about getting the celing level or atleast much closer to level then it is now.
I figure one option is a permanent beam pole in the middle of the garage from floor to ceiling, but Id like to avoid that. I was hoping I could rent/buy a suitable jack and slowly lift the ceiling main beam and joists back to level and hold it there with large metal plates + bolts as I figure the beam is sagging because of the butted joints in the 2x6 main beam instead of it being one single piece of lumber spanning
What I dont get is how would you actually install those plates once the beam was jacked, to me I would want large long plates, say 4 feet loong sandwiched on both sides of the beam, but how would you install it with the joists butting up against the beam every 24"?
Just hoping to get some options, here are a few pics to show how it is constructed, I will gladly get any other pictures asked for. I plan to have a dump bin dropped off this week to begin ripping out all of the old osb/garbage/workbenches/cardboard insulated walls
Front left corner just inside the garage door looking back towards back right side
Back right corner looking towards front left
They are run on 24" center and right now the previous owner placed OSB ontop of the joists and then a ton of insulation up there to try and insulate the garage. The OSB and insulation will be coming out as its seen better days, aswell as all of the old electrical/garage door openers. But I am unsure of how to go about getting the celing level or atleast much closer to level then it is now.
I figure one option is a permanent beam pole in the middle of the garage from floor to ceiling, but Id like to avoid that. I was hoping I could rent/buy a suitable jack and slowly lift the ceiling main beam and joists back to level and hold it there with large metal plates + bolts as I figure the beam is sagging because of the butted joints in the 2x6 main beam instead of it being one single piece of lumber spanning
What I dont get is how would you actually install those plates once the beam was jacked, to me I would want large long plates, say 4 feet loong sandwiched on both sides of the beam, but how would you install it with the joists butting up against the beam every 24"?
Just hoping to get some options, here are a few pics to show how it is constructed, I will gladly get any other pictures asked for. I plan to have a dump bin dropped off this week to begin ripping out all of the old osb/garbage/workbenches/cardboard insulated walls
Front left corner just inside the garage door looking back towards back right side
Back right corner looking towards front left
