Gonna be custom making new shop from scratch and plans are for two jib cranes.
Did a while theead years ago about a retro jib crane install I did in my shop that’s a baseplate freestanding one. Busted out concrete, 4x4x4’ hole with rebar cage and anchors sticking out.
New ones, if I acquire the jib cranes before floor is poured, can I buy tubular steel that sleeve fits my jib crane od, and sink that 4 foot into my new floor with same rebar cage and massive cutout and have just a hollow tube sticking out of floor then? Drop crane in from top and then true and weld...... would save floor room without baseplates, only 12” tube sticking up
Cranes will be .5-1 Ton with 12’ ish reach
Would also allow me to buy shorter cranes and once I cut off bracing I could have floor stub sticking up extra to gain height....
A foot of engagement with several plug weld locations down low and full bead at sleeve matchup would be more than adequate
Did a while theead years ago about a retro jib crane install I did in my shop that’s a baseplate freestanding one. Busted out concrete, 4x4x4’ hole with rebar cage and anchors sticking out.
New ones, if I acquire the jib cranes before floor is poured, can I buy tubular steel that sleeve fits my jib crane od, and sink that 4 foot into my new floor with same rebar cage and massive cutout and have just a hollow tube sticking out of floor then? Drop crane in from top and then true and weld...... would save floor room without baseplates, only 12” tube sticking up
Cranes will be .5-1 Ton with 12’ ish reach
Would also allow me to buy shorter cranes and once I cut off bracing I could have floor stub sticking up extra to gain height....
A foot of engagement with several plug weld locations down low and full bead at sleeve matchup would be more than adequate