Construction started about three weeks ago, and is moving right along, it's 32'X48', with an additional 8'X10' room on the back for the air compressor, blast cabinet and parts washer. There will also be a 8'X38' porch on the back. The walls are 12'.
The floor and foundation were pored, the floor is 6" of 3000psi concrete. Wire mesh was used in the floor and rebar around the parmeter and well as a concrete beam down the center of the floor.
Framing completed and OSB in place.
Roof trusses installed
The floor and foundation were pored, the floor is 6" of 3000psi concrete. Wire mesh was used in the floor and rebar around the parmeter and well as a concrete beam down the center of the floor.
Framing completed and OSB in place.
Roof trusses installed