So the wife and I should be closing on our second house this week or early next week. My current place has been scabbed together as I went and I have most of my requirements figured out by now. Also, having a garage that was barely 300 sq ft sucked. I was really hoping to find a 3 car, but we found a house that works and the garage is a two car plus. It's roughly 450 sq ft, so about 50% bigger than what I have right now. Plasma tables eat up a ton of footage...
The one big bummer is that the garage floor is cracked and lifted beyond repair. I was hoping to just come in and epoxy the floor and move my stuff in, but it looks like instead of that, I get the have the floor re-poured. Good thing my wife works in construction.
So, as soon as I get keys, we are having a concrete guy come in and remove the old floor, over-ex about 2 inches of fill, then repour with a vapor barrier and re-bar. I was hoping to epoxy the floor before I moved in, but looking at info, it seems you need about 30 days for the concrete to cure, which I won't have, so it will have to be done at another time.
I will also be re-doing all the electrical. My buddy is an electrician and will be installing a new 200A panel in the house and pulling a 100A sub to the garage for me, with plenty of 220V and 110V along with a 3 phase circuit off of a phase converter for my equipment.
I will also be installing drywall and painting, running lines for compressed air, using a couple HF 44" boxes for a bench build.
The action starts once I get keys. I have a rough layout of where most of the stuff will go. Stay tuned.
https://scontent-a.**.fbcdn.net/hphotos-frc3/t1.0-9/10259736_10152404425889168_470109787577157393_n.jpg
The one big bummer is that the garage floor is cracked and lifted beyond repair. I was hoping to just come in and epoxy the floor and move my stuff in, but it looks like instead of that, I get the have the floor re-poured. Good thing my wife works in construction.
So, as soon as I get keys, we are having a concrete guy come in and remove the old floor, over-ex about 2 inches of fill, then repour with a vapor barrier and re-bar. I was hoping to epoxy the floor before I moved in, but looking at info, it seems you need about 30 days for the concrete to cure, which I won't have, so it will have to be done at another time.
I will also be re-doing all the electrical. My buddy is an electrician and will be installing a new 200A panel in the house and pulling a 100A sub to the garage for me, with plenty of 220V and 110V along with a 3 phase circuit off of a phase converter for my equipment.
I will also be installing drywall and painting, running lines for compressed air, using a couple HF 44" boxes for a bench build.
The action starts once I get keys. I have a rough layout of where most of the stuff will go. Stay tuned.