An update - the doors were finished today, two 9x8 doors and a 18x8. The 9x8 in the lift Bay Area had to follow the roof pitch - which was a 6 pitch. They installed the track and door today I think it came out well.




Next up is electrical which is scheduled to be completed Friday. I have given them a short punch list : gutters, final grade around foundation, door jam corrected and several other small items. Then the driveway to be done. Hopefully in the next week or so.
I have a long list growing on my whiteboard to get started on as soon as they finish and turn it over to me:
- paint ceiling
- insulate / sheet walls / paint
- install Derek Weaver 10k 2 post lift
- fab small closet and sound insulate for compressor
- deal with floor - haven't decided yet
- move in
List goes on lol