Looking for some tips here. I am building a shed and putting sheathing on the walls. The Sheathing is placed vertical and I am using 2-3/8" ring shanked nails in a pneumatic gun.
Where the 2 plywood panels **** together (with 1/8" gap), I am having a heck of a time from keeping the nails from blowing out through the stud. I spent half my time last night pounding the nails back out. Its like they hit the grain and fly out the 3.5" side of the 2x4 stud. Am I doing something wrong?
The shed won't be finished off, so I don't want any nails poking through.
Where the 2 plywood panels **** together (with 1/8" gap), I am having a heck of a time from keeping the nails from blowing out through the stud. I spent half my time last night pounding the nails back out. Its like they hit the grain and fly out the 3.5" side of the 2x4 stud. Am I doing something wrong?
The shed won't be finished off, so I don't want any nails poking through.