I appreciate all the positive comments on this over the last year. It’s been extremely frustrating and I’ve done my best to remain calm (for the most part) regarding the matter. I did come unglued with the builder and his salesman at one point but it could have been worse.
I’m going to point out what was done and resolved. For those that say, “you should have done this or made them do this, etc., etc.”. I consulted with an attorney and engineers many times on this matter. They explained the best course of action was to be firm, educated about the situation and let the builder resolve the issue without legal action. They said that is the ideal course of action. He explained the cost of taking this to court would escalate quickly. In fact, depending on what a ******* match it might become, could approach the cost of the structure. So that would not really be an option.
So in the end, I got the engineers on my side, and got some 3rd party engineering/construction recommendations and continued to remind the builder of that fact. I’m absolutely positive he knew if it did go to court, he would lose so he did pretty much what the engineer recommended. So I’m going to point things out step by step. As I posted before, I’m trying to keep this positive. So if you have nothing positive to add, please don’t comment.
The head engineer was very knowledgeable and knew right away what the problems were. As some have posted in previous comments and as I found from 3rd parties, we all knew this, the wall was not constructed properly, fill was not done properly. He said even though the wall was an issue, the fill was the root of the problem. He said since it was not filled in lifts, it settled massively. When holes were drilled to check the settling, one side of the garage, there was 6” of air gap between the fill and concrete. He said the slab was sliding over to the side pushing the wall out.
He had the footings excavated to inspect and they looked fine.
He did soil compact test of the dirt around the footings and found it to be just fine.
His recommendations were the following:
*Excavate the entire perimeter and install new footings. Not sure why but these were at least twice and wide as the previous.
*Install a new wall around existing wall. This walled was core filled and laterally reinforced with rebar. Wall was capped.
*Most of garage floor was busted out. The front part was OK and was the footer for the front of the garage.
*Holes were drilled into existing slab and rebar crossed to opposing walls. New concrete poured in remainder. I have since painted the outside walls.
In the course of this, they had to move my electrical, cable line etc. With the cost of the new footers, walls, concrete, electrical cont., downspouts, this must have cost them significantly. He was not happy about it, I was not happy about it but it got done finally.
So I finally started some forward progression on my other projects. Got 50 sheets of drywall delivered and 2 guys came and hung all of it in 6 hours. Another two guys came the next day and did the mud. Had it done in a day and came back another day and finished. They were awesome, looks better than the drywall in my house. You can’t see a single seam!
I painted and got most of the trim done.
Hung some T8 lights (not sure how I’m wiring yet, so wiring is temp). Started to work on the window trim. Should be done this winter with all of that.
Building workbenches over X-mas vacation.
Bought my epoxy floor but too cold to apply. That’s the 1st project in the spring.
Having gone through this, my best recommendation would be to ask for references (many) and talk to them before choosing a builder. In my case, it was a very reputable home builder that does nice work. However, they attempted to start another sub company to construct garages and let some people run it that had no business running a construction business. The engineer (who was really open and honest with me) said they now have him approve everything before they construct a garage. So apparently they learned a very expensive lesion.
It’s finally nice to post some positive stuff after all of this. I have a thousand pics of what they actually did but posting the main things. I will add to the progression of this over the next few months.