First post on this forum. Looking for feedback on my initial plan to power up my new barn.
Routing 2-2-2-4 AL SER from 200A main panel (in basement) to junction box mounted to 2x12 joist, butted against the 2x12 bond. Feeder protected by 90A breaker in panel. No conduit because of the twists, turns, gas lines, plumbing and there are many existing holes in joist structure. Feeder will be run in parallel with HVAC trunk line. Apparently this is allowed (no conduit) since feeder is larger than 6 AWG. The run in the basement is approx 30'.
Splice 2-2-2-4 MHF in junction box for the run to the barn (straight through/pull configuration). Pass the MHF through hole in bond, bend it 90 degrees to go underground using a 2" PVC Transition. Glue a piece of 2" PVC onto the transition into the ground. Finally, direct bury the MHF out to the barn at 18" (approx 45').
Questions:
1. Can I simply use bushings on the junction box or is something else more elegant required to protect the conductors?
2. Can I **** the J-box directly against the bond, and run the MHF directly through the bond and into the transition?
3. Should I consider mounting the Box on Outside the house?
4. What would you do differently?
Thanks - Glenn
Routing 2-2-2-4 AL SER from 200A main panel (in basement) to junction box mounted to 2x12 joist, butted against the 2x12 bond. Feeder protected by 90A breaker in panel. No conduit because of the twists, turns, gas lines, plumbing and there are many existing holes in joist structure. Feeder will be run in parallel with HVAC trunk line. Apparently this is allowed (no conduit) since feeder is larger than 6 AWG. The run in the basement is approx 30'.
Splice 2-2-2-4 MHF in junction box for the run to the barn (straight through/pull configuration). Pass the MHF through hole in bond, bend it 90 degrees to go underground using a 2" PVC Transition. Glue a piece of 2" PVC onto the transition into the ground. Finally, direct bury the MHF out to the barn at 18" (approx 45').
Questions:
1. Can I simply use bushings on the junction box or is something else more elegant required to protect the conductors?
2. Can I **** the J-box directly against the bond, and run the MHF directly through the bond and into the transition?
3. Should I consider mounting the Box on Outside the house?
4. What would you do differently?
Thanks - Glenn