Im having a 54x83 pole building shop put up by Morton for my business and I have afew questions.
Im building it on a lot that was woods (in IL) in november, and I cut all the tree's down where my building needed to go, and pushed the stumps out with a bulldozer, pushed dirt back in the holes and tried to pack them down as good as possible with the tracks (39,000# 750C Deere Dozer). It has frozen and thawed since then, and im worried about insufficient compaction and settling for pouring the floor in the building
any tips on how to get the earth compacted enough so I can pour asap.
a local rental place has vibrating sheeps foot packers from walk behind sizes all the way up to the huge riders that are for road building..
one concern is a packer too big will float over the holes..
any help/tips would be great
Im building it on a lot that was woods (in IL) in november, and I cut all the tree's down where my building needed to go, and pushed the stumps out with a bulldozer, pushed dirt back in the holes and tried to pack them down as good as possible with the tracks (39,000# 750C Deere Dozer). It has frozen and thawed since then, and im worried about insufficient compaction and settling for pouring the floor in the building
any tips on how to get the earth compacted enough so I can pour asap.
a local rental place has vibrating sheeps foot packers from walk behind sizes all the way up to the huge riders that are for road building..
one concern is a packer too big will float over the holes..
any help/tips would be great