Hello all......the project begins and I have a big question about the masonry sequence.
The finished garage will have a four post car lift and the design of the second floor calls for one support post at the stairwell wall to hold the interesection of two girder trusses.
Fir these 5 locations (1 truss support and 4 car lift posts) we decided to pour cement footings/pads that are 30"x30" x 36" deep (overkill I know but we are riverfront and the subsoil down near the Jersey shore is pure sand)
My question is WHEN do these footings/pads get poured so that they are level with the finished floor and do they need to be pinned to the slab? At the sam time the block wall footings are poured? I don't understand the sequence and timing of the process.
Thanks!
Jeff
The finished garage will have a four post car lift and the design of the second floor calls for one support post at the stairwell wall to hold the interesection of two girder trusses.
Fir these 5 locations (1 truss support and 4 car lift posts) we decided to pour cement footings/pads that are 30"x30" x 36" deep (overkill I know but we are riverfront and the subsoil down near the Jersey shore is pure sand)
My question is WHEN do these footings/pads get poured so that they are level with the finished floor and do they need to be pinned to the slab? At the sam time the block wall footings are poured? I don't understand the sequence and timing of the process.
Thanks!
Jeff