So we are in the process of replacing our current 8x10 saltbox style shed with a new 12x16 cape style. The primary reason for this upgrade is due to the T1-11 siding on the 8x10 being in direct contact with the ground, thus causing rot and animals to invade our lawnmower, popup tents, snowblowers and pretty much everything else that's housed inside. This is going to be a long process since we are building it in stages. The design was drawn up by myself and my wife, but after some discussion and site review (after the umpteenth time) we have revised the design yet again.
I am open to any suggestions, should you have any.
Running Tab:
$120 (Site Prep, Piers, Perimeter Framing, Joist hangers)
$120 (2x8x12 Joists)
$50 (Miscellaneous)
$70 (Stone)
$2,100 (Walls, Roof, T1-11 Ply, CDX, Shingles, Drip edge, vents, trim...etc)
$2,410 Total!!
Plans:
PT 2x8 framing (Joists will be blocked as well)
PT 3/4 plywood flooring
PT 2x4 bottom sill
2x4 doug fir or pine walls
T1-11 siding with possibly OSD behind it (Not sure yet)
2-35 3/4" x72" Fiberglass Shed Doors (Need to Find)
2/3 24x27 vinyl windows (buying at http://ecobuildingbargains.org/ ) So its what ever they have in stock
Truss system from a local lumber yard for the roof
I am going to prep for power, but not 100% set if I will run it or not.
Timeline:
Site prep: 8/15
Frame: 9/12
Walls: Spring 16
Completion: Spring 16
Pictures:
This is with the joist hangers 16" OC and the outside frame squared with corner gussets (correct term?)
I am open to any suggestions, should you have any.
Running Tab:
$120 (Site Prep, Piers, Perimeter Framing, Joist hangers)
$120 (2x8x12 Joists)
$50 (Miscellaneous)
$70 (Stone)
$2,100 (Walls, Roof, T1-11 Ply, CDX, Shingles, Drip edge, vents, trim...etc)
$2,410 Total!!
Plans:
PT 2x8 framing (Joists will be blocked as well)
PT 3/4 plywood flooring
PT 2x4 bottom sill
2x4 doug fir or pine walls
T1-11 siding with possibly OSD behind it (Not sure yet)
2-35 3/4" x72" Fiberglass Shed Doors (Need to Find)
2/3 24x27 vinyl windows (buying at http://ecobuildingbargains.org/ ) So its what ever they have in stock
Truss system from a local lumber yard for the roof
I am going to prep for power, but not 100% set if I will run it or not.
Timeline:
Site prep: 8/15
Frame: 9/12
Walls: Spring 16
Completion: Spring 16