v1rot8
Member
Hi all,
Longtime lurker and used many of your ideas, so thank you.
Almost done, just flooring and a/c. My slab has some flaws, so I have ground and diamond ground the slab.
Looking for advice on filling the low spots and over the expansion material along the edges where exposed.
I ordered the Rustoleum Pro and should get it next week. Any ideas that will last under the epoxy and not take 28 days to cure? I would like to paint by next Wed.
Thanks
Here is my intro thread with some pics for advice compensation.
http://www.garagejournal.com/forum/showthread.php?t=102936
Here are some repair area pics.
low spot
Low spot and expansion material
Longtime lurker and used many of your ideas, so thank you.
Almost done, just flooring and a/c. My slab has some flaws, so I have ground and diamond ground the slab.
Looking for advice on filling the low spots and over the expansion material along the edges where exposed.
I ordered the Rustoleum Pro and should get it next week. Any ideas that will last under the epoxy and not take 28 days to cure? I would like to paint by next Wed.
Thanks
Here is my intro thread with some pics for advice compensation.
http://www.garagejournal.com/forum/showthread.php?t=102936
Here are some repair area pics.
low spot
Low spot and expansion material