Sounds like jblnut has you mostly covered regarding the fiber. But I would also encourage you to run 1-1/4" conduit instead of 1". And run innerduct inside the conduit. The I/O cable will be fine.
I dont see where I ever mentioned 1" conduit.
Above I posted 1.5"(to guarantee the large sweep bends).
1.25 or 1.5, the cost difference is probably negligible.
The guy on the UI forum recommended running the fiber in 1.25" PE sprinkler line which you can buy bulk rolls of for stupid cheap...but im pretty sure my builder wont go for that and will only offer gray conduit. If I was doing it myself the PE sprinkler line is an interesting option, but this will be run and stubbed up through the concrete pour on both sides so im like 99% sure the builder will only use actual gray conduit.