Getting close to laying a slab, but I need some advice that I haven't been able to find 100% answer for. For some background:
http://www.garagejournal.com/forum/showthread.php?t=204177
One of the problems that started out was that our sewer line is only 20" below grade. That meant 4" tube would be required. (only need 1/8" rise!)
https://scontent-b.**.fbcdn.net/hphotos-frc3/1380751_815011279150_1167877532_n.jpg
Its also 74' from the entrance to the garage.
https://scontent-b.**.fbcdn.net/hphotos-prn2/1385430_815011368970_1335484362_n.jpg
Luckily the garage is above grade, where the 6" of gravel is actually above grade. that gives me 26" from bottom of concrete.
74' * 1/8" rise = 9.25" from sewer line to entrance to the garage.
So from the base to the garage I have about 16.75" to work with. However, since the grade slopes down a little, I really only have about 12" to work with.
My question comes down to this, can I run vents vertically from the mainline according to this photo? Each has a vent, but the shower and WC vents will have water flowing through them potentially...
Also, what are the rules about running a 1/2" PEX line across ABS pipe under a slab? I keep seeing rules saying you must space them out if you're using unapproved materials under a grade... but I thought both PEX and ABS are approved?
http://www.garagejournal.com/forum/showthread.php?t=204177
One of the problems that started out was that our sewer line is only 20" below grade. That meant 4" tube would be required. (only need 1/8" rise!)
https://scontent-b.**.fbcdn.net/hphotos-frc3/1380751_815011279150_1167877532_n.jpg
Its also 74' from the entrance to the garage.
https://scontent-b.**.fbcdn.net/hphotos-prn2/1385430_815011368970_1335484362_n.jpg
Luckily the garage is above grade, where the 6" of gravel is actually above grade. that gives me 26" from bottom of concrete.
74' * 1/8" rise = 9.25" from sewer line to entrance to the garage.
So from the base to the garage I have about 16.75" to work with. However, since the grade slopes down a little, I really only have about 12" to work with.
My question comes down to this, can I run vents vertically from the mainline according to this photo? Each has a vent, but the shower and WC vents will have water flowing through them potentially...
Also, what are the rules about running a 1/2" PEX line across ABS pipe under a slab? I keep seeing rules saying you must space them out if you're using unapproved materials under a grade... but I thought both PEX and ABS are approved?
