I had my sub panel inspection earlier this week. For reference, my sub panel is 200' away from the main panel, I pulled two hots, one neutral and a ground, all in proper conduit, buried to depth. When we walked out to the sub panel, he said I couldn't use the ground from the main panel and I had to remove it, and use the grounding rods I sank as the only ground. Everything I've read points to this as being incorrect, is it? He approved the installation, but I want to make sure it's done properly and with the greatest amount of safety as possible.

FYI: They are using 2014 NEC
Thanks

FYI: They are using 2014 NEC