Stripping has continued on last Friday's placement. Here is the front of the terrace wall. You can see most of the electrical boxes for the lights that will illuminate the walkway to the dock. Finish grade is at the top of the site retaining wall on the left and bottom of the architectural concrete on the right. A set of stairs will run down between them.
We also continued excavation along the front of the house. The lower wall creates the terrace. The higher wall is the house itself
There is a an organic layer at the original topsoil grade about 8' below the finish floor of the house. We covered it with fill when we raised the site grade. Per the recommendations in our geotechnical report, we are now excavating down to remove it. Wish I knew then what I know now.
The weather has turned on us again but the guys don't like to miss work so they build tents.
Placed concrete around noon. A tough job made tougher when the weather *****. I must have missed the memo regarding today's dress code. I was wearing a gray rain jacket.
Also crawled up over the hill with the excavator to see if we could get some backfilling done behind the garage.
We got most of the back as high we could before we need to add another course of sand against the waterproofing.
With all that wet clay, my operator was rightly concerned he would slide into the hole so we decided to finish up under dryer conditions.