Re: The Lone Beech Garage Build Thread (60x46)
Continued...

The plumbers were on the site installing a condensate line from the Rinnai Water Heater to the exterior of the building.

The line went from the west wall of the Mezzanine and followed the 30-Foot I-Beam to the east wall of the Lone Beech Garage.
So today a few little items were knocked out. Tomorrow morning I'm hoping we'll get the inspection for the plumbing and insulation behind us. After that the Drywall Crew should be able to get started. The wild card is the weather... it is raining hard as I write this tonight. I'm not sure how that might affect a drywall delivery tomorrow.
Scott
Continued...

The plumbers were on the site installing a condensate line from the Rinnai Water Heater to the exterior of the building.

The line went from the west wall of the Mezzanine and followed the 30-Foot I-Beam to the east wall of the Lone Beech Garage.
So today a few little items were knocked out. Tomorrow morning I'm hoping we'll get the inspection for the plumbing and insulation behind us. After that the Drywall Crew should be able to get started. The wild card is the weather... it is raining hard as I write this tonight. I'm not sure how that might affect a drywall delivery tomorrow.
Scott
Last edited: