About to move into my new 40x80 (woohoo!) shop has a dedicated two phase service with only a 100A panel with about 5 or 6 receptacles on it, that's it, not even any lights. There is also no meter in the socket right now. Before I have a meter installed and start running my electrical, I am thinking I will upgrade to a 200A panel. I figure it will be much easier to upgrade now with a virtually blank canvas then to wait till I run out of available amperage in the future. Can anyone tell me what the precautions are that I should take before going to install a new panel? Can I check to see if the service will handle the increased amperage, or is this something I need to verify with my PoCo? If that checks out can I simply swap out the panel and have the meter set, then proceed wiring my building? If I do have to contact the PoCo to verify the service, will they want an inspection done on the panel before installing the meter? Thanks in advance!!
Marvin
Marvin