Can a Monolithic garage pour be prepared by the owner if they have a skid steer, and basic construction and plumbing skills? I remember a member here talk about a contractor he knew that removed rebar from basements after the inspector had approved it right before the pour to use on the next cookie cutter house. lol
Anyway.. I wouldn't attempt a flat pour myself.. But I could see doing the digging, building and staking forms and installing the plumbing/rebar myself. I would consider it a advantage, because no short cuts could have been taken if I'm not around the day of the pour.
Thoughts or first hand experiences?
Thanks
Anyway.. I wouldn't attempt a flat pour myself.. But I could see doing the digging, building and staking forms and installing the plumbing/rebar myself. I would consider it a advantage, because no short cuts could have been taken if I'm not around the day of the pour.
Thoughts or first hand experiences?