  1. W

    Brazos River Shop

    Thats awsome, Im in the process of putting up a Mueller bolt together....42'x50'x16'. I'm doing it myself, so progress is slow. I look forward to getting to the point you are at! woodweasel
  2. W

    Mueller red iron complete

    also there are no tracks,per say this is a commercial style roll up,
  3. W

    Mueller red iron complete

    I did plan for the doors,and the proper steel is in place.The roll up doors are under my barn.My question was should I install them before or after I put up the sides and roof. I'm a Captain on a tugboat,I won't be back home until the 23rd.Hence no progress no pics😃
  4. W

    Mueller red iron complete

    Is there a way to combine my posts into one? Also remember the key is do unsafe acts SAFELY:thumbup: I'm sure OSHA would not have approved of some of the things involved in erecting this building:lol_hitti
  5. W

    Mueller red iron complete

    Ready to put in walk in doors& windows,then start insulation&sheetmetal. I'm thinking of putting 12 x12 roll ups last, any advice?Yes,No,??
  6. W

    Working on my Mueller Erection,pics

    Its in central Texas, Robertson County.A little town called Franklin. Scroll down to see the other pic I posted. Its titiled the same. Bought the building in Bryan, 42 miles away.
  7. W

    Working on my Mueller Erection,pics

    :Its 42x50 , that includes a 12' lean to. the rafters are indeed up sidedown. Took me a while to figure that out! I had to take all three back down & rebolt them together! Thats why I was happy to finally get to this stage!! I now can read the blue prints a little better! Ha! there are some more...
  8. W

    Polish garage project

    I noticed your stack of boards had stickers between them to allow for drying. Did you cut them? Or did you buy the wood green. I have a sawmill and was just wondering? Woodweasel
  9. W

    Working on my Mueller Erection,pics

    Was pretty happy with my progress as I had a ragtag group of guys helping.Not to mention had never done this before����
  10. W

    Working on my Mueller Erection,pics

    Started erecting the red iron,
  11. W

    Working on my Mueller Erection,pics

    Started erecting the red iron,
  12. W

    slab finished

    well the slab is finished and I started laying out the beams.Never used blueprints before so it's going slowly.Hopefully I'll start erecting at the end of the month.It's a Mueller 40'x52'prefab.I have poured a 8'x12' extension of the building on one side for my head and storage use. I did not...
  13. W

    Starting my building

    just starting the groundwork on my building. I wound up ordering a 42 "x 50" prefab from Mueller.30"x50" will be in closed and insulated.12"x50" will be covered.not much on the pictures as of yet will post more later!
  14. W

    Pulled The Trigger On New Shop In Texas

    Doug heres a couple of pics of mill.Ironic that you live in Cypress, will be doing a job there later this month:beer:
  15. W

    Pulled The Trigger On New Shop In Texas

    central texas- poe dump town of Franklin!! I love it!!
  16. W

    Pulled The Trigger On New Shop In Texas

    As my title said I did it!! I went with a Mueller Pre-Fab 30'x 50' with a 12' Lean to or shed on the 50' side. Slab will be 42'x50'. I am doing alot of the concrete work as well as erecting the building. ( Never put up a metal building:headscrat)I have a couple of buddies who are concrete guys...
  17. W

    Erecting A Mueller Building

    Hi. New to the site. Fixing to pull the trigger on a Mueller Building.It will be set on a slab which I will pour. 42'x50' total slab. 30'x50' enclosed 12'X50' open (just roof & slab).I'm pretty much a handyman an will put up building also.Thought this would be a great place for some pointers...