My build is continuing along. Electrical rough is ongoing. Hopefully the rough inspection will be signed off by Friday, so that we can insulate the walls next week. Electrical is taking longer than I thought, but we are doing more in-wall than I had initially planned. Hopefully this means there will be less electrical to do after the walls are closed in.
Prep for the concrete apron is ongoing. Hoping to get that poured by Friday.
Prep for the concrete apron is ongoing. Hoping to get that poured by Friday.