I continue to work away at some of the less rewarding tasks.
I was able to get a load of gravel delivered which is rare this time of year since everything is frozen. Unless you want a full truck straight from the quarry you’re usually out of luck. A big thank you to GeeTee for delivering 2 yd3! I was able to fill the trench and feel better about my kids walking over it.
I’m sealing the vapour barrier around all the outlets and seams. AcoustiSeal is terrible but it works - enough said. I’m due for another inspection when this is all done. Then I’ll be ready for drywall.
Electrical should be completed this week, I’ll post another update then.
I moved in the workbenches that were left over from my concrete forms. They are temporarily balanced on whatever I could find along the whole 40’ wall. Great to have so much horizontal surface, it will be a commitment to not let things pile up.

Photos from opposing corners, don’t mind the mess for now.